Putnam Avenue, West Prospect Street, and Mills Terrace
October 21, 2020 Paving is scheduled on these streets. Today, blacktop grinding was in the process of completion.
Lower Prospect Street and Broadway (30A)
October 20, 2020 crews will complete the blacktop grinding in preparation for blacktopping the street once infrastructure repairs are completed.
October 21, 2020, we have tree removal scheduled for this street. Also, DPW crews will prepare sidewalk areas to replace blacktop sidewalks that do not meet Village codes and where sidewalks are cracked or damaged from construction.
October 27, 2020, Broadway will be closed to through traffic – residents will be allowed up to each side of construction on Broadway.
Paving Lower Prospect Area
Once the work extends out into Broadway is complete, we expect the blacktop company to pave Lower Prospect Street. The paving should occur sometime between October 27th and the first week of November.